Home > News > Anglicare Warrina 5 ILU’s – Progressing at an exceptional rate
Anglicare Warrina 5 ILU’s – Progressing at an exceptional rate

Anglicare Warrina 5 ILU’s – Progressing at an exceptional rate

August 25, 2017

The Anglicare Warrina 5 project at the Castle Hill Facility is progressing at an exceptional rate with both Building 1 and 3 ground slabs being poured.

The formwork for Building 1 level 1 slab is erected and it is scheduled to be poured next week.

Building 3 level 1 formwork has commenced with the concrete pour scheduled for early September.

90% of in ground services are complete allowing scaffold to be erected to both buildings.