The Anglicare Rooty Hill Stage 1 team is tracking well and on program with all four buildings coming out of the ground.

All CFA piles and in ground services have been completed for the Residential Care Building, with footings and lift pit to be poured tomorrow and basement Dincel walls to commence early next week.

All CFA, screw piles and 75% of detailed excavation for Residential Living 1 & 2 Buildings are complete with in ground hydraulic and electrical services progressing.

The Community Centre Building earthworks are complete with in grounds services due to commence.

The significantly sized OSD tank (36m x 36m) being poured today.

News & Updates

View All Articles

Subscribe for upcoming news and events

  • This field is for validation purposes and should be left unchanged.

Contact

+61 2 9955 7000
lipman@lipman.com.au
Level 6, 66 Berry Street,
North Sydney
Locked Bag 2106
North Sydney NSW 2060

Licence

Builder’s License 27970
ABN 84 001 548 830